Education Project Experience
Park Hill South High School Additions and Renovations
LOCATION: Parkville, Missouri
DESCRIPTION: As part of the district's 2022 bond, a new addition was constructed at Park Hill South High School. This addition provides students with a new gymnasium that doubles as a storm shelter, along with a weight room, pre-function entry, band and theatre areas, and reconfigured parking. The football field was also updated with new grandstands and a press box.
COMPLETION: August 2025
COST: $21,993,657
Blue Valley School District- District Office Renovation
LOCATIONS: Overland Park, Kansas
DESCRIPTION: The Blue Valley School District Office Renovation consisted of a full interior renovation completed in four carefully planned phases to maintain daily operations throughout construction. This phased approach allowed faculty and staff to remain in the building while work was completed, eliminating the need for temporary relocation and minimizing disruption to district services.
Each phase was strategically sequenced to isolate construction areas from occupied spaces, prioritizing safety, accessibility, and clear communication. The project included demolition and reconstruction of interior spaces, updated office layouts, new finishes, and coordination of building systems to support the renovated environment. Through this phased delivery, the project improved efficiency and workflow within the facility while maintaining a fully functional workspace for staff. The result is a modernized district office that better supports daily operations and long-term district needs.
COMPLETION: July 2025
COST: $344,891
Park Hill High School Additions and Field Renovations
LOCATION: Kansas City, Missouri
DESCRIPTION: A new two-story athletic addition was constructed at Park Hill High School, consisting of a weight room, offices, and locker room spaces on the first floor, along with a gymnasium, restrooms, and a new corridor on the second floor. A new scene shop and storage space were also added to the school’s Performing Arts Theater, and interior renovations were completed in the theater and art rooms.
Exterior improvements included a new softball field, dugouts, an athletic field building, parking lots, and fencing. Additionally, an expansion to the Park Hill Aquatic Center provided new locker room areas, restrooms, offices, and storage space.
COMPLETION: August 2025
COST: $30,423,676
Lafayette County C-1 School District
LOCATIONS: Higginsville, Missouri
DESCRIPTION: Over the summer of 2024, secure vestibule renovations were completed at the Lafayette County C-1 School District Middle and High School, reconstructing their entrances to provide safer and more secure access at each location.Additions and renovations were also completed at the front entrance of Lafayette County C-1 School District Grandview Elementary School. This project included a new secure vestibule, reception area, principal’s office, and testing space. Renovations also provided a new conference room, as well as a nurse’s office with a restroom and storage room.
COMPLETION: August 2025
COST: $2,460,381
Kansas City Public Schools
LOCATIONS: Kansas City, Missouri
DESCRIPTION: We have an active Master Services Agreement with Kansas City Public Schools. It is a three year contract with each project close to $1M in construction cost. We provide construction support that cover all 30 buildings. Pictures illustrate improvements to East High School's theatrical lighting system.
COMPLETION: Ongoing
CONTRACT AMOUNT: $7.9 Million
MCC Agricultural Annex
LOCATION: Kansas City, Missouri
DESCRIPTION: We constructed a new building for Metropolitan Community College's new agriculture program. The building holds new offices, a new classroom, lab, and greenhouse. The greenhouse has all new features including automated shades and lighting systems, environmental controls, and irrigation.
COMPLETION: March 2025
COST: $5,021,434.87
Piper School District- Early Childhood Center + Piper Creek Elementary Renovations
LOCATION: Kansas City, Kansas
DESCRIPTION: The Piper School District Early Childhood Center and Piper Creek Elementary renovations consisted of extensive interior demolition and reconstruction to modernize the facilities and enhance the learning environment for young students. The project focused on improving functionality, safety, and overall aesthetics across both campuses. Scope of work included removal of existing walls, ceilings, flooring, doors, cabinetry, and building systems, followed by installation of new metal stud framing, insulation, drywall, and upgraded mechanical, electrical, and plumbing systems. Masonry improvements were completed with new walls supported by structural steel lintels, along with installation of new door frames and hardware.Additional improvements included roofing patchwork, installation of new sewer lines with slab removal and replacement, updated acoustical ceiling systems with new lighting and ductwork, and installation of durable finishes including epoxy flooring, carpet tile, and rubber base. These upgrades provide a safer, more efficient, and modernized environment tailored to early childhood and elementary education.
COMPLETION: August 2024
COST: $2,216,417
Hickman Mills School District Improvements
LOCATION: Kansas City, Missouri
DESCRIPTION:
Roof improvements, restroom renovations, HVAC improvements, Parking Lots and Sidewalks, Secure Entries, Fine Arts, Athletics, Exterior Improvements, Ceiling Improvements, Interior Painting, and Playground Turf.
COMPLETION:
2022
COST: $30,000,000
Lexington Schools
LOCATION: Lexington, Missouri
DESCRIPTION:
• Addition of new commons and food service
• Elevator installation
• Renovation of old food service area to new special education classrooms and resource space
• Miscellaneous upgrades to existing classrooms and administrative areas
COMPLETION:
2022
COST: $5,765,000
LOCATION: Kearney, Missouri
Lee's Summit School District
LOCATION: Lee's Summit, Missouri
DESCRIPTION:
Two-story interior renovations to existing building that includes all demolition, architectural, structural, and MEPFT upgrades to be turned into Paradise Park Early Education Center
Interior renovations to existing Fire Station building that includes all demolition, architectural, structural, and MEPFT upgrades to be turned into Environmental Science Building
Exterior upgrades including prefabricated restroom unit, fishing dock, nature trail, site signage, playground equipment, and utilities
COMPLETION:
2023
COST: $13,555,000